
The podium portion of the second phase has been poured. Six storeys high, it will be clad in yellow brick like phase one. Windows and exterior walls are being put in place. Plumbing drains have been installed on the first two floors. There will be a seven floor tower on top of this podium, to be located at the end of the building just past the crane.
Closer up, showing the new wing attached to the existing building at the small triangular ledges that were put in place for phase one.